Connect 9996666 Nipple and 9998339 Manometer. Where necessary, 9998493 Hose may be used between the nipple and the manometer. Test run the engine at full load in order to check max boost air pressure.
Removal NOTICE! Be prepared to gather up fluids. 1 Drain the coolant entirely of sufficiently for the level to be below the e-EGR coolant pipe; refer to Coolant, Change page 187. 2 Remove the check valve according to Non-return valve e-EGR, change page 163. 3 Remove the coolant pipe, outlet, from the e-EGR cooler.
Shangchai SC7H230D2 diesel electric generator set technical data include Shangchai engine & alternator detailed parameters.
2 Remove the hose (1) between the inlet manifold and the charge air cooler. Remove the electrical connection (2) from the pre-heater relay. Remove the connector (3) from the preheater element. Remove the electrical connection (4) from the charge air pressure sensor.